CMA Terminals Khalifa Port phases and port-level capacity

Sources checked

Track the terminal and port milestonesKhalifa Port and the CMA terminal expansion
  1. December 2024
    Initial CMA terminal opens

    1.8 million TEU annual design capacity · First phase Source 1

  2. 2025
    CMA terminal handles its first operating-year volume

    1.3 million TEU handled · Actual Source 1

  3. 2025
    Whole Khalifa Port throughput

    6.6 million TEU handled · Actual Source 2

  4. 18 November 2025
    CMA CGM and AD Ports agree to expand

    AED 420 million announced investment · Agreement Source 1

  5. Early 2028
    Expanded CMA terminal scheduled

    2.7 million TEU annual design capacity · Target Source 1

  6. Early 2028
    Whole Khalifa Port capacity after expansion

    10.5 million TEU annual design capacity · Target Source 1

The timeline distinguishes annual design capacity from the actual containers handled in 2025.

Source 1 Source 2 Source 3

CMA Terminals Khalifa Port phases and port-level capacity

TEU means twenty-foot equivalent unit. Actual throughput is a period count. Annual design capacity is an infrastructure rating. The early 2028 figures are the operator’s scheduled targets.

6 records
Source
December 2024Initial CMA terminal opens1.8 million TEU annual design capacityFirst phaseSource 1
2025CMA terminal handles its first operating-year volume1.3 million TEU handledActualSource 1
2025Whole Khalifa Port throughput6.6 million TEU handledActualSource 2
18 November 2025CMA CGM and AD Ports agree to expandAED 420 million announced investmentAgreementSource 1
Early 2028Expanded CMA terminal scheduled2.7 million TEU annual design capacityTargetSource 1
Early 2028Whole Khalifa Port capacity after expansion10.5 million TEU annual design capacityTargetSource 1