Published milestones and equipment measures for the Salalah upgrade

Sources checked

Expansion milestonesFrom the first crane deliveries to the reported expansion
  1. February 2024
    First ship-to-shore cranes arrive

    4 of 10 delivered Source 1

  2. June 2024
    Final ship-to-shore delivery reported

    Last 4 arrive, with 4 older units being retired Source 2

  3. October 2024
    First hybrid yard cranes roll into service

    4 of 12 planned units Source 3

  4. February 2025
    Expansion milestone announced

    Capacity increased from 4.5 million to 6.5 million TEU Source 4

  5. February 2025
    Quay and yard package described

    6 existing berths upgraded, with 2,000 additional reefer plugs Source 4

The timeline distinguishes equipment arriving during construction from the later capacity announcement.

Source 1 Source 2 Source 3 Source 4

Published milestones and equipment measures for the Salalah upgrade

Capacity is the operator’s annual handling estimate. The February 2025 account updates the figures used in the 2024 construction announcements.

5 records
Source
February 2024First ship-to-shore cranes arrive4 of 10 deliveredSource 1
June 2024Final ship-to-shore delivery reportedLast 4 arrive, with 4 older units being retiredSource 2
October 2024First hybrid yard cranes roll into service4 of 12 planned unitsSource 3
February 2025Expansion milestone announcedCapacity increased from 4.5 million to 6.5 million TEUSource 4
February 2025Quay and yard package described6 existing berths upgraded, with 2,000 additional reefer plugsSource 4