Jeddah’s South Container Terminal handled more than 221,200 TEU in July 2026, including 79,720 TEU of exports. Its operator also reported added handling equipment and a separate logistics park under development near the terminal.

Sources checked

July 2026 containers handledJuly 2026 throughput and the export component
  • Total terminal throughput, lower bound221,200 TEU
  • Export throughput within total79,720 TEU

Exports are already included in total throughput.

Source 1 Source 2

Exports were about a third of the July record

The terminal reported more than 221,200 TEU in July, its highest month under DP World since 1999. Exports accounted for 79,720 TEU, roughly 36% using the rounded total as a base. The balance includes other flows, and the release does not separately quantify July import and transshipment containers. Source 1

The first-half figures describe a different period

The operator recorded 390 vessel calls in January to June and says total volumes rose nearly 79% year on year across imports, exports and transshipment. That growth rate covers six months. The 221,200 TEU threshold instead describes July alone, so the two numbers cannot be combined into a growth series. Source 1

Cold cargo depends on power and enclosed space

The operator’s terminal profile describes a US$13 million investment in temperature-controlled capability. It gives 5,000 reefer plugs, twice the previous 2,500, and 75 reefer chambers versus seven before. A plug provides power to a refrigerated container during storage. The chamber count describes separate handling infrastructure. Source 2

The park and terminal expansion measure different capacity

DP World says further terminal work is intended to reach 5 million TEU in annual handling capacity. It separately describes a 415,000 square metre logistics park development priced at US$250 million. Space for warehousing and inland distribution and container handling through the terminal address different constraints. Source 1